Adding BaselineFields in My Assignment View

C

c.tambone

Hello,

I would like to know how in Project 2007 I can customize the "My
assignment" page in order to view the Baseline Work information. It
seems this info is not available in this specific View.
If the field is not available in this view, do you know of a
workaround in order to get the Baseline Work info displayed in the My
Task page but also in the Update page for the Project Manager?

Thanks for helping me out!
 
D

Dale Howard [MVP]

c.tambone --

I'm afraid that the Baseline Work field is not available to add to the My
Assignments page in PWA. I do not know of a workaround either. Sorry.
 
C

c.tambone

c.tambone--

I'm afraid that the Baseline Work field is not available to add to the My
Assignments page in PWA. I do not know of a workaround either. Sorry.










- Mostra testo tra virgolette -

Is there a way then to customize the Preview Gantt Chart table in the
Task Update page? What I need is really point out for the Project
manager the comparison between Work and Baseline Work in order for him
to know what happende through the timesheet phase.

Thanks
 
Top