Chris --
Each project manager will need to open every project and do the following:
1. Click Tools - Customize - Published Fields
2. Add whatever Baseline field (Baseline Work?)you have inserted in the
Timesheet view and click OK
3. Click Collaborate - Publish - Republish Assignments and click OK
Completing the above steps will "push" the values in the field to each
user's timesheet. Again, each project manager must do this for EVERY
project he/she is managing. Hope this helps.
Chris Walsh said:
I want to add the baseline column in the timesheet view, adds sucessfully
but when a user view's the weekly timesheet the baseline column is blank!
even though the project has been baselined and can be viewed in Portfiolo
Analyser???