Adding columns to Task Summary in PWA

L

Linda Corbet

Is there a way to add the resource column to the Task Summary report shown
when you go to Project Center and select a project? I realize it's under
different views but wanted to add it to that report. Thanks.

L
 
G

GirlGeek

Is there a way to add the resource column to the Task Summary report shown
when you go to Project Center and select a project? I realize it's under
different views but wanted to add it to that report. Thanks.

L

Hi, Linda,

Someone with Administrator permissions would need to customize a view
for you. Click on Admin, Manage Views, then copy the Task Summary
Report and modify it to add the Resource column. Name it Summary with
Resources or Custom Summary or <your company initials> Summary (you
get the idea). Save. You should then see the new view when you select
a project.

Aviva
 
Top