Adding Different Times and Showing It in the Gantt Chart

T

Té

I'm trying to add different work hours for each day 8-12, 1-5, 6-9. These
are the hours for each day. I've changed the working time, however, it
doesnt show up on the Gantt Chart. How can I see this on the Gantt Chart?
 
M

Mark Everett | PMP

I'm trying to add different work hours for each day 8-12, 1-5, 6-9.  These
are the hours for each day.  I've changed the working time, however, it
doesnt show up on the Gantt Chart.  How can I see this on the Gantt Chart?

Te,

As Jan says, but to be more clear, the table data on the left side and
the Gantt area on the right side can each be controlled by a different
calendar. If you use a custom calendar (in Projects > Project
Information) for the table you need to be sure you use the same
calendar on the Gantt, using Jan's instructions.

Regards,
Mark Everett