Adding fields on PWA

N

Nat

Hi,

How do I add other fields in the timesheet view that
resources can update on the Web?

Ie. Resources can update actual work and remaining work
for a task but, I would also like them to update the field
physical % complete. I know how to add the field in the
view but no input can be made in it from the Web.

Thanks!
 
D

Dale Howard [MVP]

Nat --

Each project manager will need to open every one of his/her projects and do
the following:

1. Click Tools - Customize - Published Fields
2. Copy the Physical % Complete field to the list on the right
3. Select the "Let resource change field" option for the field
4. Click Yes when prompted with a warning dialog
5. Click the OK button
6. Click Collaborate - Publish - Republish Assignments
7. Click OK

Hope this helps.
 
N

Nat

Great! It worked!

Thanks!
-----Original Message-----
Nat --

Each project manager will need to open every one of his/her projects and do
the following:

1. Click Tools - Customize - Published Fields
2. Copy the Physical % Complete field to the list on the right
3. Select the "Let resource change field" option for the field
4. Click Yes when prompted with a warning dialog
5. Click the OK button
6. Click Collaborate - Publish - Republish Assignments
7. Click OK

Hope this helps.







.
 
Top