S
straforel
The OVERALLOCATION column becomes YES when tasks a resource is assigned
to overlap. The table text also becomes red in the Resource Sheet and
Resource Usage views.
I would like to identify resource allocation for an additional
scenario: when events a resource is assigned to do not occur in the
correct order. For example, there are three events which should happen
after one another:
Task 1 >> Task 2 >> Task 3
(although these are not linked by a predecessor relationship)
If the same resource is assigned to all 3 tasks and Tasks 2 occurs
after Task 3 (but does not overlap), is it possible to identify this as
a problem?
Thanks!
STR
to overlap. The table text also becomes red in the Resource Sheet and
Resource Usage views.
I would like to identify resource allocation for an additional
scenario: when events a resource is assigned to do not occur in the
correct order. For example, there are three events which should happen
after one another:
Task 1 >> Task 2 >> Task 3
(although these are not linked by a predecessor relationship)
If the same resource is assigned to all 3 tasks and Tasks 2 occurs
after Task 3 (but does not overlap), is it possible to identify this as
a problem?
Thanks!
STR