Jean-Pierre --
Team members can propose new tasks in a project, but they cannot be added to
the project until you approve the New Task request. Team members cannot
directly change the Start or Finish date of a task, or the Duration of the
task, but they can indirectly change the Start, Finish, and Duration of the
task by the information they enter in their timesheet.
For example, you assigned me to a task full-time (40 hours of Work) and the
task was scheduled to begin on this past Monday and was supposed to Finish
today (Start = 2/9/04, Finish = 2/13/04, and Duration = 5 days). On my
timesheet, I entered 8 hours of work each day on Wednesday and Thursday only
(16 hours total), and I changed the Remaining Work estimate from 24 hours to
40 hours (because I will have to redo the work). In other words, I started
two days late so the task will finish two days late. However, because I
increased the Remaining Work estimate by 16 hours, the task will finish a
full four days later than originally scheduled. Therefore, after submitting
my actuals to you for this task and after you update my actuals into the
project plan, the Start date will be 2/11/04 and the Finish date will be
2/19/04 with a Duration of 7 days. Hope this helps.