Adding Task IDs to Email Notifications

K

Kevin Fleischhaker

There are two features that would be very useful to me

1) Customizing the email reports to include Task ID’s
2) Allowing resources to enter custom project fields (such as Date 1)
through Project Web Access

Can anyone help?

Thanks
 
R

Reid McTaggart

Resources, if given Open and Save permissions, can use the Edit button in the
Project Center to change values of customized Enterprise Project Date fields
(and certain other types of Enterprise Project fields as well).
 