Cecile --
Because the Remaining Work field is not a default Portfolio Analyzer field,
you must add the field as a custom calculated field. To do so, complete the
following steps:
1. Open a Portfolio Analyzer view for modification in PWA
2. Click the Calculated Totals and Fields button at the top of the
PivotTable section
3. Select "Create Calculated Total" from the shortcut menu
4. Name the new field "Remaining Work"
5. Delete the 0 from the formula workspace area
6. Click the field drop down list button in the lower right corner of the
dialog and select Work (Total)
7. Click the Insert Reference To button
8. Insert a minus sign (-) to the right of the [Measures].[Work] field
9. Click the field drop down list button again and select Actual Work
(Total)
10. Click the Insert Reference To button
11. Click the Change button
12. Click the Format tab
13. In the Number field, type the following number format including the
quotes: ###,##0.0"h"
14. Close the Commands and options dialog
Hope this helps.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"