You cannot, at least within the defaults of the Portfolio Analyzer. Only
enterprise Project and Resource outline code fields are included as
dimensions in the OLAP cube. To do anything else requires custom
development work. Hope this helps.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado http://www.msprojectexperts.com
"We wrote the book on Project Server"