I want to use a project again. I changed all the tasks to 0% complete. Act
Start then changes to NA. When I run the Adjust dates function I get a
message "One or more tasks have actuals". About 25 tasks out of 180 do not
adjust to the new Project Start Date. I can't see any actuals in the tasks
that wouldn't move - any idea whats going on?