I believe the other option available if you are using an administrative plan
to track sick time is to have his/her resource manager adjust the hours in
pwa.
1. On the Resource Center, choose to Adjust Actuals
2. Select the resource name
3. Update the individuals timesheet
4. Choose the "update actuals" button to submit the change
This assumes the proper security settings allow resource managers to perform
this function for their team members.
John