hi,
i got several msp files by my collegues without resource planning. Now
i want to add resource planning and have to adjust the canlendars.
Therefore, i set the dailywork from 8hrs to 6,4hrs and the weeklywork
from 40hrs to 32hrs. However, as i do that, i dont want, that the
existing dates and durations change. Everything shall stay the same,
except that i define the working hrs new, to calculate the needed
manpower later.
How can i do that?
Furthermore, another question. Why can i define a workday from 8am to
5pm with an hour break, but still define the dailywork with 6,4hrs. What
is the definition of the start and end for? Do i have any consequences
through this difference between the 6,4hrs defined and the 8hrs defined
through the start and endhours? (simular, when i define 6hrs a day, 5
days, but 32hrs a week? how does that work?)
thx a lot rgds, manuel
i got several msp files by my collegues without resource planning. Now
i want to add resource planning and have to adjust the canlendars.
Therefore, i set the dailywork from 8hrs to 6,4hrs and the weeklywork
from 40hrs to 32hrs. However, as i do that, i dont want, that the
existing dates and durations change. Everything shall stay the same,
except that i define the working hrs new, to calculate the needed
manpower later.
How can i do that?
Furthermore, another question. Why can i define a workday from 8am to
5pm with an hour break, but still define the dailywork with 6,4hrs. What
is the definition of the start and end for? Do i have any consequences
through this difference between the 6,4hrs defined and the 8hrs defined
through the start and endhours? (simular, when i define 6hrs a day, 5
days, but 32hrs a week? how does that work?)
thx a lot rgds, manuel