Adjusting hours

B

benny

I want to be able to have to sets of hours in my project on project server.
I want to have the hours bid and hours completed and I want to have a
seperate hours called "actual hours" that shows how many real hours I put it.

So I can see the difference in hours by how much I bid and how much I
actually used.

Thanks,

Ben
 
S

Steve House [Project MVP]

How does "hours completed" differ from "real hours put in?" Sounds like
they'd be the same thing to me.
 
B

benny

Let say I show that I bid 30 hours for a project, but I was effiecent and got
it done in 15.

I want the project to show 100% completed and show it only took me 15 hours
instead of the complete 30.
 
J

Jan De Messemaeker

Hi,
Use the columlns actual work and remaining work
Put actual work to 15 and remaining work to 0; Enter.
HTH
 
B

benny

Where would I find these columns at? Do I need to change some configuration?

Thanks for the help
 
S

Steve House [Project MVP]

Take a look at the Tracking Table (View menu, Tables, Tracking). Actual
Work is already there - right click on a column heading and insert the
Remaining Work column.
 