B
Buzz
Is there a way to make sure Remaining Work does not go up,
when time is taken out of the timesheet. For example, I
have a resource with no Remaining Work, left on a
particular task. They mistakenly enter 8 hours on 12/3
and 8 hours on 12/4. When they replace the 8s with zeros,
to correct the mistake, the Remaining Work changes to 16.
Is there a way to make sure this does not happen with
future mistakes?
Thanks,
Buzz
when time is taken out of the timesheet. For example, I
have a resource with no Remaining Work, left on a
particular task. They mistakenly enter 8 hours on 12/3
and 8 hours on 12/4. When they replace the 8s with zeros,
to correct the mistake, the Remaining Work changes to 16.
Is there a way to make sure this does not happen with
future mistakes?
Thanks,
Buzz