"Administrative Project" in Data Analysis?

D

Darrell

When using the Project List in Data Analysis the "Administrative Project"
that tracks the admin categories is not included. Is there a way to add it?

Darrell
 
T

Tom B

If you build your Data Analysis view from the TIMESHEET cube the ADmin
project shows up...it is not reported in the other 2 OLAP cubes (EPM
TIMESHEET and MSP_PROJECT_TIMESHEET)
 
M

MShayeb

Hi Tom
when you view the cube the administrative times appers Auto generated ?? is
this a problem with my server or this is the way it works and is there anyway
to show the real administrative time name ?
 
T

Tom B

There will be an attribute called 'timesheet class' that will breakdown the
contents of the Administrative time project that will give you the actual
names of all the classes of Admin time (below the line) on the timesheet.
This way you can drill into the Admin project plan, and see the amount of
time between vacation, bereavement, sick time, holiday time, etc. Hope that
helps?
TomB
 