Administrative project

K

KON

hi

1- How to work with Administrative projects (i.e.
Vacation, training)that will be affected to all resources
of all projects?

2- I want to add a work field in a tasks section along
with Duration and that will be applicable to all project
templates.It sounds like i need to save this
configuration in enterprise level.Can anybody help me out?

-Kon
 
G

Gary L. Chefetz \(MVP\)

Mike:

The fix is finished; hooray! I should have the KB reference number in the
next day or so.

--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts

-
ITG_Mike said:
I would not use the "Assign Myself" function as described here.

There are MANY bugs in the self assignment code and I can assure you that
your time submissions WILL get corrupted. I have documented the details of
this for Microsoft and they are working on a fix. I have posted other
messages that discuss this problem. This is not an issue with Admin
projects, but with self-assignment in general.
 