J
John M.
I have noticed that the combined actual work and remaining work on
Administrative projects are displayed in the Assignment Remaining Work field
on the PWA Timesheet view - with the Actual Work field = 0, and the % Work
Complete field = 0%.
This is obviously not how the data is stored in the work plan; so is this
done for Admin projects in PWA purely so that the tasks are not displayed as
being "Completed" and are available for team member time entry even when
filtering for incomplete tasks?
Just curious.... Thanks!
John
Administrative projects are displayed in the Assignment Remaining Work field
on the PWA Timesheet view - with the Actual Work field = 0, and the % Work
Complete field = 0%.
This is obviously not how the data is stored in the work plan; so is this
done for Admin projects in PWA purely so that the tasks are not displayed as
being "Completed" and are available for team member time entry even when
filtering for incomplete tasks?
Just curious.... Thanks!
John