M
MattLT
In the book Project2003 inside-out page 697 (7), resources
for admin projects are associated a little differently
than other project types.
It states that after assigning resources (in the desktop
client), don't assign them to any of the administrative
tasks. This does tend to agree with the new PWA Task
Action: 'Notify your manager of any time you will not be
available for project work' ---
BUT IT DOES NOT SEEM TO WORK.. and error msg stating that
there are no currnet assignments to an administrative
project appears.
When I go back and add the resources to tasks in the
normal way it does appear to work. So is the book wrong,
then if so, why was the the PWA task action above added..??
Matt
for admin projects are associated a little differently
than other project types.
It states that after assigning resources (in the desktop
client), don't assign them to any of the administrative
tasks. This does tend to agree with the new PWA Task
Action: 'Notify your manager of any time you will not be
available for project work' ---
BUT IT DOES NOT SEEM TO WORK.. and error msg stating that
there are no currnet assignments to an administrative
project appears.
When I go back and add the resources to tasks in the
normal way it does appear to work. So is the book wrong,
then if so, why was the the PWA task action above added..??
Matt