Mark Byington
If a project resource designates dates for Vacation (example) and then the PM
assigns that resource to a task that is scheduled over those dates, it
doesn't look like the designated dates and considered 'non-working' days
(like Saturday and Sunday in the Standard Calendar) and the task is not
scheduled around those dates. It seems to me, this should be the case withou
the need to level the resource. Any way to make this happen?
If administrative projects don't work in this manner, what is the advantage
to creating them?