Allocating 50% of work on Mondays and Thursdays

E

ET

Hi,

How can I allocate 50% of work for a resource on Mondays and Thursdays?
For the rest of the days, he will be working 100%.

Thx in Advance,
ET
 
M

Mike Glen

Hi ET,

Welcome to this Microsoft Project newsgroup :)

I would change his calendar so that he was working mornings on Mondays and
Thursdays, and assign him at 100% throughout.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
J

Jim Aksel

There is another method that may also work. In the Task Usage View manually
adjust the hours on Mondays and Thursdays. This will allow you the
flexibility to schedule other work for this employee if they are working
other activities on the same project. For example, they may attend "Material
Review Board" on Monday & THursdya for half a day and then work on "Quality
Inspection" for the remainder.

Either method will work, Glen's may be shorter.
 