I'm having a problem in MS P 2010. I have a resource who is available
to my project 50% of the time. I have given him a Max allocation in
the resource sheet of 50%.
I'm trying to allocate a task to him that I know will take 8 hours.
If he was available to me a full day - say June 30th, I know he would
complete the task in that day.
However, since he's available half time, I expect him to do half a day
on June 30 and half on July 1. Currently my project is showing
completion on June 30, (as though I had him for the full day).
How can I fix this so his allocation spills into July 1?
Thanks,
Chris
I'm having a problem in MS P 2010. I have a resource who is available
to my project 50% of the time. I have given him a Max allocation in
the resource sheet of 50%.
I'm trying to allocate a task to him that I know will take 8 hours.
If he was available to me a full day - say June 30th, I know he would
complete the task in that day.
However, since he's available half time, I expect him to do half a day
on June 30 and half on July 1. Currently my project is showing
completion on June 30, (as though I had him for the full day).
How can I fix this so his allocation spills into July 1?