F
Frank
hello again,
i am trying to allocate my resources - but i have 8
projects on wich most of them are booked and there on
individual tasks - no i would like to allocate them on the
projects in terms of percentage of time they are sceduled
to spend there - thus i would like to say 30% of
resource "A" on Project "1" and 20% of the same
resource "A" on project "2" ...
in thouse projects i want the project manager to then book
the resource "A" on specific tasks but only inside the to
the project assigned percentage.
how can i do that?
can anyone help
thanks
Frank
i am trying to allocate my resources - but i have 8
projects on wich most of them are booked and there on
individual tasks - no i would like to allocate them on the
projects in terms of percentage of time they are sceduled
to spend there - thus i would like to say 30% of
resource "A" on Project "1" and 20% of the same
resource "A" on project "2" ...
in thouse projects i want the project manager to then book
the resource "A" on specific tasks but only inside the to
the project assigned percentage.
how can i do that?
can anyone help
thanks
Frank