D
DavidM1L
Hi, I'm a bit new to MSP 2003 (Pro), so I may have some "conceptual"
problems still with things, but can anyone help me out with this
question?
If I have a bunch of tasks, can I get project automatically to add
resources to them based on some form of work type and skills grouping?
For example, if I have a task called "digging", can I identify that as
"manual labour" so if I then have resource called "Joe" identified as
a "manual labourer" MSP can then automatically add him to the task and
adjust dates etc. if he's free to do it?
I realise resource levelling does some of this, but I'd just like to
check if I can't simply add tasks, tag them, then add resources, tag
them, then hit "allocate these resources to these tasks".
Thanks for any tips.
Dave
problems still with things, but can anyone help me out with this
question?
If I have a bunch of tasks, can I get project automatically to add
resources to them based on some form of work type and skills grouping?
For example, if I have a task called "digging", can I identify that as
"manual labour" so if I then have resource called "Joe" identified as
a "manual labourer" MSP can then automatically add him to the task and
adjust dates etc. if he's free to do it?
I realise resource levelling does some of this, but I'd just like to
check if I can't simply add tasks, tag them, then add resources, tag
them, then hit "allocate these resources to these tasks".
Thanks for any tips.
Dave