Shawn Mc
What's the best way to schedule these tasks? I have 5 devlopers tasked with
developing 40 webpages. The designs for the pages will be provided to the
team and team members will grab one from the top of the pile, develop and
test it, then grab another one. If resoruce 1 is faster than resource 2,
he'll develop the pages faster, etc.
As the project rolls on, we'll add perhaps another 20 pages and one or two
more devs as needed.
I have each of the webpages, along with 4 subtasks for each, in the schedule
and am preparing to assign resources.
How do the experts recommend I do this to permit flexibility yet accurately
track progress?
developing 40 webpages. The designs for the pages will be provided to the
team and team members will grab one from the top of the pile, develop and
test it, then grab another one. If resoruce 1 is faster than resource 2,
he'll develop the pages faster, etc.
As the project rolls on, we'll add perhaps another 20 pages and one or two
more devs as needed.
I have each of the webpages, along with 4 subtasks for each, in the schedule
and am preparing to assign resources.
How do the experts recommend I do this to permit flexibility yet accurately
track progress?