Our current Analysis server is reaching the end of its life cycle and we are
replacing it with a new one. From looking at the literature it doesn't seem
to require any changes to Project Server any changes have to be done on the
SQL server side.

Has anyone else here done this migration? Are their any problems I need to
anticipate?
 
P

Paul Conroy

If you're using the same netbios name for the server, then there are no
actions required. (remember to apply to appropriate roles to the new cube).

if you are changing the server name you will need to alter the server name
in each views that references the cube.

If you are upgrading to AS2005 then you will need to create a repository
manually. email me [email protected] for instructions.
 