Mark
To assist with planning, a number of upcoming projects were scheduled
using generic resources. The result is a number of over allocated
generic resources (not a problem) and fractional generic resources per
time period. For example, the use of a generic resource "Developer"
on all projects in March 2005 might result in 5.28 "Developers"
required.
I have been asked if the analysis functions can automatically round up
the resource needs. My gut reaction is that it cannot and we should
export the view to Excel to do further analysis.
Is that correct?
Thanks in advance,
Mark
using generic resources. The result is a number of over allocated
generic resources (not a problem) and fractional generic resources per
time period. For example, the use of a generic resource "Developer"
on all projects in March 2005 might result in 5.28 "Developers"
required.
I have been asked if the analysis functions can automatically round up
the resource needs. My gut reaction is that it cannot and we should
export the view to Excel to do further analysis.
Is that correct?
Thanks in advance,
Mark