I have my organization tracking Application support hours against a year long
project plan. When the plan is originally set up, we set tasks to fixed work
and indicated each resource estimated units at say, 20%. When a resource
enters hours against their tasks and the PM approves it we are noticing that
the % units is being automatically adjusted. How can this be avoided? Are
we better to set at fixed units, not effort driven to avoid this automatic
adjustment when time is entered against tasks?