S
Steve Schacher
I'm looking for an enhancement to leveling that behaves like Project
Workbench's contour pattern that will fill in remaining gaps with time
from a task.
I want to be able to assign resources to baseline tasks with fixed
percents of time, and also be able to assign them to additional fixed
work tasks at whatever availability is left and then let the leveler
find the time to schedule the task by reducing the daily work to
whatever is needed to reach the resource's max availability. I'm
guessing that the best way to do this is by enhancing the usage of
contour patterns on an assignment by assignment basis. Currently, I
have to look at a resource's histogram to see what their percent
allocation is during the periods in question and then enter the
remaining percent as the units for the assignment. I'd like to see MSP
enhanced to do this for me if I set a designated contour pattern.
Any chance of MSP satisfying this need (want?) in a future release?
Steve Schacher
ChevronTexaco
Workbench's contour pattern that will fill in remaining gaps with time
from a task.
I want to be able to assign resources to baseline tasks with fixed
percents of time, and also be able to assign them to additional fixed
work tasks at whatever availability is left and then let the leveler
find the time to schedule the task by reducing the daily work to
whatever is needed to reach the resource's max availability. I'm
guessing that the best way to do this is by enhancing the usage of
contour patterns on an assignment by assignment basis. Currently, I
have to look at a resource's histogram to see what their percent
allocation is during the periods in question and then enter the
remaining percent as the units for the assignment. I'd like to see MSP
enhanced to do this for me if I set a designated contour pattern.
Any chance of MSP satisfying this need (want?) in a future release?
Steve Schacher
ChevronTexaco