G
GUY
Good day,
I am working in a program composed of 100 sub-projects.
I want to use external links with the PROGRAM schedule.
In total, I expect to have in average 5 external links per projects all
linked to PROGRAM schedule.
This could end-up with 500 external links from 100 sub-projects all linked
to the same file.
Do MS Project 2003 can handle this case?
What about EPM 2007, will it be better or worst from a performance point of
view?
I am working in a program composed of 100 sub-projects.
I want to use external links with the PROGRAM schedule.
In total, I expect to have in average 5 external links per projects all
linked to PROGRAM schedule.
This could end-up with 500 external links from 100 sub-projects all linked
to the same file.
Do MS Project 2003 can handle this case?
What about EPM 2007, will it be better or worst from a performance point of
view?