Hi,
Newbie here again!
The site, and the post here are great! Thank you to everyone!
Our PM's have a concern/ interest regarding leveling.
Questions Group 1.
- We have resource 'X' shared on Project 1 and Project 2.
- Project 1 has priority 700, and Project 2 priority 500.
- We level, with just Project 1 open, Project 2 is not open.
- How does MSPRO 2003 take into account the shared resource 'X' on the
summary task?
- Does MSPRO2003 evaluate the priority of project 2, for resource X, if only
Project1 is open?
- What happens to the resource X when the project 2 has a higher prioroty
versus lower priority?
Questions Group 2.
-Can we level the projects individually, highest to lowest?
-Will this make a difference in our leveling results, or should we open all
the projects then level?
Your thoughts?
Newbie here again!
The site, and the post here are great! Thank you to everyone!
Our PM's have a concern/ interest regarding leveling.
Questions Group 1.
- We have resource 'X' shared on Project 1 and Project 2.
- Project 1 has priority 700, and Project 2 priority 500.
- We level, with just Project 1 open, Project 2 is not open.
- How does MSPRO 2003 take into account the shared resource 'X' on the
summary task?
- Does MSPRO2003 evaluate the priority of project 2, for resource X, if only
Project1 is open?
- What happens to the resource X when the project 2 has a higher prioroty
versus lower priority?
Questions Group 2.
-Can we level the projects individually, highest to lowest?
-Will this make a difference in our leveling results, or should we open all
the projects then level?
Your thoughts?