Any way to see per task whether it's dependency or resource constrained?

T

tdemelle

This may be an easy one, but it's not obvious to me. :) Is there an eas
way to see per task whether it's dependency or resource constrained
 
J

Jim Aksel

In Project 2007 you may use Project/Task Drivers from the main menu. In
Project 2010 you will be able to use the "Task Inspector" to accomplish the
same thing.

No such feature in P2003. I do, however, have some macros that will do
this... they are not freeware.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 
Top