B
Bud
Hello
I am inheriting a rather large schedule thousands of tasks and a large
number of resources 150+. It's only been up and running for about 6 weeks.....
This schedule currently is missing a few pred/succ, has many resources
concurrently scheduled half of which are greater than 5tasks being done at a
time and it is set up as fixed work. Many overallocations right now.
I think I need to do the following
1. Get the pred/succ in line so they make sense
2. Look into all this concurrent scheduling and reduce it down drastically
to where people are working on 3 or less tasks concurrently at any given time.
3. Perhaps change from fixed work to fixed units. Am thinking this because
that way I don't have to concern myslef to much with units moving. I have a
baseline.
Do you agree with this changing to fixed units or doesn't it matter?
4. Use the Resource leveling to manage overallocations but do it on a month
to month basis. seems to help with not moving out the end date as much.
Do you agree with the above 4 items?
Is there any views/filters at all that will help with managing the
overallocation?
Is there any views/filters that would help in limiting like the resource
usage view to resources that have many tasks assigned concurrently and not
show the rest?
Is there anything else views/filters or anything that would assist in
managing a very large schedule?
Thanks
I am inheriting a rather large schedule thousands of tasks and a large
number of resources 150+. It's only been up and running for about 6 weeks.....
This schedule currently is missing a few pred/succ, has many resources
concurrently scheduled half of which are greater than 5tasks being done at a
time and it is set up as fixed work. Many overallocations right now.
I think I need to do the following
1. Get the pred/succ in line so they make sense
2. Look into all this concurrent scheduling and reduce it down drastically
to where people are working on 3 or less tasks concurrently at any given time.
3. Perhaps change from fixed work to fixed units. Am thinking this because
that way I don't have to concern myslef to much with units moving. I have a
baseline.
Do you agree with this changing to fixed units or doesn't it matter?
4. Use the Resource leveling to manage overallocations but do it on a month
to month basis. seems to help with not moving out the end date as much.
Do you agree with the above 4 items?
Is there any views/filters at all that will help with managing the
overallocation?
Is there any views/filters that would help in limiting like the resource
usage view to resources that have many tasks assigned concurrently and not
show the rest?
Is there anything else views/filters or anything that would assist in
managing a very large schedule?
Thanks