Anyone manage large schedule? What is best way to set up and manag

B

Bud

Hello

I am inheriting a rather large schedule thousands of tasks and a large
number of resources 150+. It's only been up and running for about 6 weeks.....

This schedule currently is missing a few pred/succ, has many resources
concurrently scheduled half of which are greater than 5tasks being done at a
time and it is set up as fixed work. Many overallocations right now.

I think I need to do the following

1. Get the pred/succ in line so they make sense
2. Look into all this concurrent scheduling and reduce it down drastically
to where people are working on 3 or less tasks concurrently at any given time.
3. Perhaps change from fixed work to fixed units. Am thinking this because
that way I don't have to concern myslef to much with units moving. I have a
baseline.

Do you agree with this changing to fixed units or doesn't it matter?

4. Use the Resource leveling to manage overallocations but do it on a month
to month basis. seems to help with not moving out the end date as much.

Do you agree with the above 4 items?

Is there any views/filters at all that will help with managing the
overallocation?

Is there any views/filters that would help in limiting like the resource
usage view to resources that have many tasks assigned concurrently and not
show the rest?

Is there anything else views/filters or anything that would assist in
managing a very large schedule?

Thanks
 
B

Bud

How do I send it to you

Thanks

Trevor Rabey - Perfect Project Planning said:
It is almost impossible to provide good advice about this without seeing the
project plan.
So many things could be wrong that you haven't mentioned.
If it is a real, big project and 6 weeks in, you need to jump on the
problems now so that it does not all come unraveled.
Can you send it to me?
--
Trevor Rabey
0407213955
61 8 92727485
PERFECT PROJECT PLANNING
www.perfectproject.com.au
 
B

Bud

Could you provide some general guidance and would you mind so much answering
the questions I had

Thanks
 
A

amakar

If your project schedule has only been running for 6 weeks, you may wan
to consider resource leveling, assessing the project baseline an
possibly rebaselining. This will at least give you a more realisti
schedule

My approach to resource leveling has always been to manually level eac
resource on the plan. The algorithm used in automatic leveling wil
extend your date beyond a realistic date. You can manually resourc
level by filtering on a given resource, identify overallocated tasks
and simply add additional task predecessors

Hope that helps
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top