Javier
I have a task in Project Pro that is 3 hours long. Work for that task
shows up as ".5" because we have working days set at 6 hours.
When I publish the plan, the 3 hour duration shows up as ".38" in
Project Server. I'm wondering why it doesn't show up as ".5" in
Project Server? Any thoughts on this would be appreciated.
shows up as ".5" because we have working days set at 6 hours.
When I publish the plan, the 3 hour duration shows up as ".38" in
Project Server. I'm wondering why it doesn't show up as ".5" in
Project Server? Any thoughts on this would be appreciated.