We don't want our projects to have another duration after saving to Project
Server ...
Problem with Calendar – stand alone project (attached) has a finish date
4/6/2006
Once I imported it to Enterprise, finish date has been changed to 3/30/2006
Some strange behavior that might help you to understand what’s going on:
Published project, Task 49, Confirm Requirements In/Out Scope
If you go to Calendar View, you’ll see that even though days of Nov 23, 24
and 25th are marked as non-working, task duration is calculated as if these
were working days.
How could we import an attached project so dates will remain the same ?
Server ...
Problem with Calendar – stand alone project (attached) has a finish date
4/6/2006
Once I imported it to Enterprise, finish date has been changed to 3/30/2006
Some strange behavior that might help you to understand what’s going on:
Published project, Task 49, Confirm Requirements In/Out Scope
If you go to Calendar View, you’ll see that even though days of Nov 23, 24
and 25th are marked as non-working, task duration is calculated as if these
were working days.
How could we import an attached project so dates will remain the same ?