Dale,
Thanks for your reply. It did the work. We want to know the total man
days
required to complete the summary task.
For example if you have three subtask under a summary task all starting
at
the same time and having the same duration then the summary tasks in
project
will only show the diff b/n the start and finish dates. Say the
duration
of
the three subtasks is 10 days each. Then the duration of the summary
task
will be 10 days and the man days required to complete the summary task
will
be 30 days.
Best regards,
Abraham
:
Hello,
To follow Dale's answer:
Right click on the Duration1 (or other custom Duration field) then
click
Customize Fields...
Click formula
Select the field: [Duration]
Calculation for tasks and group summary rows option: Rollup ... Sum
That's all.
But what is the use of such formula? Please tell us.
Thanks
Gérard Ducouret
"Abraham" <
[email protected]> a écrit dans le message
de
news: (e-mail address removed)...
Is it possble you can show an example of how to use the custom
duration
field to calculate the sum ofsubtask durations ?
Thanks.
:
RakeshK --
What you are seeing in Microsoft Project is correct. The Duration
of
any
summary task is NOT the sum of the Durations of the subtasks. The
Duration
of a summary task is calculated from the Start date of the earliest
starting
task to the Finish date of the latest finishing task. But if you
absolutely
need to calculate a custom Duration as the sum of the subtask
Durations,
you
would need to create a custom Duration field for this purpose.
Hope
this
helps.
Hi,
Presently the duration of a summary task is NOT the arithmetic
sum
of
the
durations of its subtasks. It is calculated as the difference
between
the
most end date and the least start date of the subtasks.
How can i show the arithmetic sum of duration of subtasks in a
summary
tasks ?
Please help.