Assign Parent to Task

P

PK

Can someone suggest how, with vba in Project 2002, I can move a row to
position it for indenting as a child under a non-adjacent task? I
don't want to cut and paste the task since doing so would change the
task's UniqueID. Thanks for advice.
 
G

Gérard DUCOURET

Hello,
<<indenting as a child under a non-adjacent task>>
That's not possible... but
You can move a task with the mouse : drag and drop, so that the Unique ID will not change.

Gérard Ducouret
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top