P
Prakash
I have resource who needs to work on a task for 3 weeks but he will work on
this task for 2 weeks, then work on another task for a week and come back to
the first task and complete the rest. In this case how should i allocate him
to both the tasks. How should by start and end dates of 1st task look like
and what % should he be assigned to the 1st task