Assign resource to the milestone task.

K

ks2008

I could able to assign resource to the milestone task.
What is that means ?
Thanks
K
 
J

Jim Aksel

It is possible to assign resources to milestones and summary tasks.
It is also not recommended by people here in this newsgroup. Since
Milestones are of 0 duration, assigning a resource to them does not create
work or cost for the program.

If you assign resources to summary tasks, it is confusing to determine how
to allocate the work in the subtasks.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top