Assign Resource - Toolbar button greyed out

R

Rhammia Immanuel

Hi!
Would appreciate if anyone can help me with this. My "Assign
Resource" button in the toolbar is greyed out and I cannot access it all from
any view. Iam using Project 2000.

What is that Iam missing here?

Thanks

Immanuel
 
J

Jan De Messemaeker

Hi,

Assign resources is greyed out from anty RESOURCE view
It will be active in any task view.
Its purpose is to help you assign resources to tasks; it will open a window
with the resources within the task view.
It doesn't help at all in a resource view.
HTH
 
R

Rhammia Immanuel

Thanks for the response. Its greyed out even in the Gantt Chart view.
Something is not right here.

Thanks.
 
J

JulieS

Hi Rhammia,

Are you looking at a split view of the Gantt Chart -- Gantt at top and
some other view at bottom? If so, and the lower pane is active (darker
blue bar at left) the Assign Resources button may not be active. Try
selecting a task in the top pane and see if that fixes it.
--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top