Assigning a group or team to a task

R

Rod

In Project / Server 2007, is it possible to create a team of individuals,
then assign the team to a task rather than each of the individual work
resources?
 
D

Dave

Rod said:
In Project / Server 2007, is it possible to create a team of individuals,
then assign the team to a task rather than each of the individual work
resources?

Yes, but it would help if you gave more details about what you are
trying to achieve.

Normally this feature would be used if you had a pool of resources of
the same skill type (programmers, welders, authors etc).

If your pool was 5 strong, you would just create an entry on the
resource sheet for the skill type and set their maximum units to 500% to
show that there were 5 of them.

They you can assign them to any task at any proportion of their
availability.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top