Assigning a resource to a summary task mean in Project Server 2003?

G

Guest

What does assigning a resource to a summary task mean?

Any thoughts on this would be greatly appreciated.

Thank you,
Shiva Chaitanya.
 
G

Gérard Ducouret

Shiva,

Some people use assignments on summary tasks for example to manage the
workload of a supervisor who is responsible for the work package under this
summary. If there are several tasks running in parallel, they don't care to
know is the supervisor is looking at a specific task.
This feature has several drawbacks, and it's considered a best practice not
to use it.

Gérard Ducouret

What does assigning a resource to a summary task mean?
Any thoughts on this would be greatly appreciated.

Thank you,
Shiva Chaitanya.
__________ Information provenant d'ESET Smart Security, version de la base
des signatures de virus 4203 (20090701) __________

Le message a été vérifié par ESET Smart Security.

http://www.eset.com



__________ Information provenant d'ESET Smart Security, version de la base des signatures de virus 4203 (20090701) __________

Le message a été vérifié par ESET Smart Security.

http://www.eset.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top