S
storm
Hi chaps
I have a project where I am going to assign a resource to a task, but
only once the first 5 days work is complete.
Please can you tell me how I show this on my plan. In the task
information section I can see where to assign the resource, but it
looks as if it assigns it for the entirety of the task.
what I need is to be able to assign both resources for 20 days, but one
resource to start 5 days after the other.
Is this possible, please? If not do I have to create two tasks to
accommodate it?
many thanks
lynne
I have a project where I am going to assign a resource to a task, but
only once the first 5 days work is complete.
Please can you tell me how I show this on my plan. In the task
information section I can see where to assign the resource, but it
looks as if it assigns it for the entirety of the task.
what I need is to be able to assign both resources for 20 days, but one
resource to start 5 days after the other.
Is this possible, please? If not do I have to create two tasks to
accommodate it?
many thanks
lynne