Theonlyrobertson
I'm trying to determine how to change resources on a given task. Often, I
have to plan to hand off a design task from one engineer to another due to
skill sets and priorities.
How can this be done within one task so that I have an accurate resource
loading picture of "who's working on what"?
Thanks,
Dale
have to plan to hand off a design task from one engineer to another due to
skill sets and priorities.
How can this be done within one task so that I have an accurate resource
loading picture of "who's working on what"?
Thanks,
Dale