P
Peter Jakab
It's possible to assign a fixed resource cost to a task by assigning the
resource to the task, then setting the units to 0 on the task form, and
entering the appropriate value into the cost field.
It works fine, but the cost entered this way is not included in the OLAP
queries in the Analyzer views.
Is it normal?
Regards
Peter
resource to the task, then setting the units to 0 on the task form, and
entering the appropriate value into the cost field.
It works fine, but the cost entered this way is not included in the OLAP
queries in the Analyzer views.
Is it normal?
Regards
Peter