Assigning Group of Resources

R

Rami

Hi

Is it possible to define a group of resources in the resource pool and
assign a task to the group?

Thanks
Rami
 
R

Rohan

Hi Rami,

I guess thats a feature coming on Project Server 2007. I dont think we have
that option in Project Server 2003.

-Rohan
 
P

Prj_Mngr

You could have a resource called "Project Team" and assign that. Then you
would have to remember how amny people are in the team to get any resource
availability
 
D

Doug P.

You would also have to up the resource availabilty. For four persons, it
would be 400%, for 3 persons in the group 300%, etc.
 