Assigning multiple reporting roles to an administrative project

S

Sheba Chungath

Hi

I am currently piloting EPM and while trying to set up
timesheet system, I ran into this situation.

I have published an administrative project which contain
common & routine activities applicable to all resources
across all projects.

Now, when they fill in actual hours and update task
details, I get the report. I want to configure MSP to send
these reports to respective project managers.

Any ideas folks?
 
K

Kasper Ovi

Hi

To get this to work, each project manager must make his own administrative
project and assign only the resources he needs to get updates from. Because
you published the project, you're automatically assigned as the project
manager and will receive all update information.

Good luck.

Kasper
 
S

Sheba Chungath

Thanks Kasper!

-----Original Message-----
Hi

To get this to work, each project manager must make his own administrative
project and assign only the resources he needs to get updates from. Because
you published the project, you're automatically assigned as the project
manager and will receive all update information.

Good luck.

Kasper




.
 
Top