D
Dennis
I was hoping to get a bit fo help:
I have been trying to set up a project file that has two
12 hour shifts with 4 of those 12 hours calulated at an
overtime rate for each shift. I can't seem to figure out
how to make this calculation automatic. I would like to
assign resources to the task as a 'Day Shift' and a 'Night
Shift' because the rates of pay between the two are
slightly different.
Is there any way that I could set up project to accomodate
this type of situation? Ideally, I would like to avoid
assigning overtime hours to individual tasks and simply
work around the clock based on regular and overtime rates
for each of the two groups.
Put another way, can I assign work around the clock and
expect project to be able to calculate costs based on a
regular and overtime rate given that the regualr rate
would apply to the first 8 hours of the shift and overtime
would apply to the remaining 4 hours of the shift?
Any guidance would be greatly appreciated.
Dennis
I have been trying to set up a project file that has two
12 hour shifts with 4 of those 12 hours calulated at an
overtime rate for each shift. I can't seem to figure out
how to make this calculation automatic. I would like to
assign resources to the task as a 'Day Shift' and a 'Night
Shift' because the rates of pay between the two are
slightly different.
Is there any way that I could set up project to accomodate
this type of situation? Ideally, I would like to avoid
assigning overtime hours to individual tasks and simply
work around the clock based on regular and overtime rates
for each of the two groups.
Put another way, can I assign work around the clock and
expect project to be able to calculate costs based on a
regular and overtime rate given that the regualr rate
would apply to the first 8 hours of the shift and overtime
would apply to the remaining 4 hours of the shift?
Any guidance would be greatly appreciated.
Dennis