J
JDC_Consulting
My client does both project and application support work. On the application
support side, they would like to treat these resources as a pool. In their
"Application Support" Project in Project Server, they would like to assign
the pool to tasks but allow an individual pool resource to record time
against the task. Project is fairly explicit about only allowing resources
that have tasks assigned to be able to report time against them.
Is is possible to assign the pool but yet have a pool resource record time
against the task? We have thought about assigning all resources in the pool
every time a new task is added. However that presents its own problems
especially if only one pool resource will end up working on the task. The
tasks in this case are small (1 to 40 hours) and they come frequently.
Any experience or options with this would be helpful.
Thanks
Jeff
support side, they would like to treat these resources as a pool. In their
"Application Support" Project in Project Server, they would like to assign
the pool to tasks but allow an individual pool resource to record time
against the task. Project is fairly explicit about only allowing resources
that have tasks assigned to be able to report time against them.
Is is possible to assign the pool but yet have a pool resource record time
against the task? We have thought about assigning all resources in the pool
every time a new task is added. However that presents its own problems
especially if only one pool resource will end up working on the task. The
tasks in this case are small (1 to 40 hours) and they come frequently.
Any experience or options with this would be helpful.
Thanks
Jeff