Gary D
I have a 20 day task called shutter, steel and concrete on a programme. I am
assigning labour resource across the whole activity, however every 4th day i
will be concreting, therefore i want to assign a concrete pump every 4th day
on this single activity. I do not want to create 5 seperate concreting
tasks. Is this possible on Microsoft Project?
-
GDD
assigning labour resource across the whole activity, however every 4th day i
will be concreting, therefore i want to assign a concrete pump every 4th day
on this single activity. I do not want to create 5 seperate concreting
tasks. Is this possible on Microsoft Project?
-
GDD